MGL Sp.z o.o.

About the project
The expansion of the MGL Sp. z o.o. plant in Rawa Mazowiecka (Phase III) involves the construction of a new 5 450 m² production and storage hall and 3 500 m² of covered manoeuvring yards, integrated with the existing factory. The project was carried out without interrupting production, using steel construction, with a high-load-bearing floor and two 10-tonne overhead cranes. The roofing of the yards was structurally designed to accommodate a photovoltaic installation, and the design incorporates enhanced resistance to extreme rainfall thanks to the expansion of the drainage and retention system. The work was carried out using BIM/3D, which streamlined coordination and implementation.
CLIENT
MGL Sp. z o.o. (MAGO Group)
TYPE OF PROJECT
Industrial – Expansion of the Production and Warehouse Facility (Phase III)
PLACE
Rawa Mazowiecka, 16 Opoczyńska Street
ARCHITECT
Kiloniuton Sp. z o.o. (Building Design) & BIMES S.C. (Detailed Design)
AREA
usable: 5,450 m² (new production hall) total: ~8,950 m² (hall + covered maneuvering areas)
VOLUME
~60,000 m³
SCOPE OF WORKS
Design & build
CONSTRUCTION PERIOD
IV 2025 – XI 2025