VALEO ENGINE COOLING

About the project
The project involved the expansion of the Valeo Engine Coolinglogistics zone in Skawina. The project included laying the foundations for a nitrogen gasification station, constructing a wasteshelter and a hazardous materials warehouse, adding an unloading hall to the existing plant, and expanding the road and maneuvering area, along with the technical infrastructure. The facility expansion utilized a steel structure protected with an anti-corrosion coating. The substructure, reinforcements, and walls were made of reinforced concrete, and the roof was insulated with mineral wool.
CLIENT
Valeo Autosystemy
PROJECT TYPE
industrial
LOCATION
Skawina
ARCHITECT
VALODE ET PISTRE
Architects
SCOPE OF WORK
Construction works
IMPLEMENTATION PERIOD
2007 - 2008