Valeo Engine Cooling
CLIENT
Valeo Autosystemy
TYPE OF PROJECT
industrial
PLACE
Skawina
ARCHITECT
VALODE ET PISTRE Architekci
AREA
CAPACITY
SCOPE OF WORKS
construction works
CONSTRUCTION PERIOD
2007 - 2008
The project concerned the expansion of the Valeo Engine Cooling logistic area located in Skawina. The scope covered the construction of foundations for the station of nitrogen gasification, execution of waste shelter and storage for dangerous materials, an unloading bay and extension of roads, manoeuvre yard and technical infrastructure. During the extension there was used the steel structure including anti-corrosion protection and final coating. The reinforced concrete structure was used for the frameworks, reinforcement and reinforced concrete walls; the roof insulation was made with the use of mineral wool.