Saint Gobain Sekurit DG

CLIENT

Saint-Gobain Sekurit

TYPE OF PROJECT

industrial

PLACE

Dąbrowa Górnicza

ARCHITECT

Budoprojekt

AREA

stage I: 11 140 m2, stage II: 9 325 m2

CAPACITY

SCOPE OF WORKS

construction works

CONSTRUCTION PERIOD

2008 - 2010

The project involved the construction of a production building with a shipping zone and technical rooms for the world leader Saint-Gobain Sekurit. Completed works involved the reinforcement of the soil under the foundations using the CFA technology, and the soil under the floor using the jet-grouting technology. The façades have been created using a light housing system, and external networks have also been installed. The facility was built on a steel structure with a total weight of approx. 44,000 kg. The ventilation function for smoke vents has also been used here: the pneumatic smoke ventilation control system consists of pneumatic actuators installed in the vents that trigger smoke removal.

Completed Construction